     The Civil Engineering and Development Department (CEDD) today (August 23) gazetted a notice to invite tenders for the contract for Kwu Tung North New Development Area, Remaining Phase: Site Formation and Infrastructure Works (North) (Contract No. ND/2024/02). The closing time for the tender is noon on November 1.

     The works mainly include:

  • site formation of lands (including site clearance and land decontamination works) and ground investigation within Kwu Tung North New Development Area (KTN NDA);
  • construction of at-grade roads within KTN NDA;
  • construction of noise barriers and low noise road surfacing; and
  • ancillary works including footpaths, cycle tracks, lighting, traffic aids, drainage, sewerage, water mains, district cooling mains, landscaping works, slope works, flood prevention works and electrical and mechanical works.

     The works are scheduled to commence in March 2025 and will take about 63 months to complete.

     The CEDD has commissioned AECOM Asia Company Limited to design and supervise the works.  Interested contractors can download the tender forms and other particulars from the e-Tendering System (e-TS). Tenderers must submit tenders in electronic format via the e-TS.

     Details of the tender notice are available on the CEDD's website (www.cedd.gov.hk/eng/tender-notices/contracts/tender-notices/index.html). For enquiries, please call AECOM Asia Company Limited at 3922 9000 during office hours.