     The Civil Engineering and Development Department (CEDD) today (June 23) gazetted a notice to invite tenders for the contract for Hung Shui Kiu/Ha Tsuen New Development Area Second Phase Development – Contract 1 – Site Formation and Engineering Infrastructure Works (Contract No. YL/2023/01). The closing time for the tender is noon on August 18.
 
     The works mainly include:

  • site clearance and formation (including land decontamination works) for about 30 hectares of lands, together with provision of associated engineering infrastructure;
  • construction of local roads connecting to Ping Ha Road, Shek Po Road and Shek Po East Road;
  • construction of a community liaison centre;
  • construction of associated works including water mains, drainage and sewerage works, district cooling mains, cycle tracks, footpaths, box culvert, landscaping works, electrical and mechanical works and other ancillary works; and
  • implementation of environmental mitigation measures (including noise barriers) and environmental monitoring works for the works mentioned above.

 
     The works are scheduled to commence in early 2024 and will take about 42 months to complete.
 
     The CEDD has commissioned Ove Arup & Partners Hong Kong Limited to design and supervise the works. Interested contractors may obtain the forms of tender and further particulars from Ove Arup & Partners Hong Kong Limited at Level 5, Festival Walk, 80 Tat Chee Avenue, Kowloon Tong.
 