Weekly Road Report – West End Ward

DUNDEE CITY COUNCIL – WEEKLY ROAD REPORT

REPORT FOR WEST END WARD WEEK COMMENCING MONDAY 20 MARCH 2017

Perth Road (at Arnhall Drive) – temporary traffic lights for one week for gas main renewal.   (However, please see my update from Scotland Gas Networks yesterday).

Blackness Road (at Rosefield Street) – temporary traffic lights for one week for Scottish Water mains renewal.

Nethergate (West Marketgait to South Tay Street) – closed for up to one week for carriageway resurfacing works.

SSE Glenagnes Cable Renewal – Lochee Road lane restrictions and closures on Blinshall Street, Fleuchar Street and Scott Street for 5 months.

Perth Road (at Springfield) – temporary traffic lights for up to one week for footway works.



Dundee City Transmission Cable Replacement Project – an update

From Scottish and Southern Electricity Networks – regarding the high voltage cable replacement project – area from Lochee Road to Logie Avenue :

“As you’ll be aware the Dundee City Transmission Cable Replacement project commenced on 6 March 2017 and is progressing according to programme.  
Below is an update in relation to the works and roads affected by these as at w/c 20 March : 
  • Lochee Road, Joint Bay 1/2 – Road remains open to traffic who are able to pass with care
  • Lochee Road, Joint Bay 2/3 – Traffic management system sees the sequencing of traffic lights staggered to accommodate single direction traffic as at 13/03
  • Fleucher Street, Joint Bay 3/4 – Fleuchar Street will close w/c 20 March.  A diversion is in place and will take approximately 1 minute by car.  Local access for residents, pedestrians, cyclists etc will be maintained during this closure. 

I’d also like to give you a bit of notice regarding abnormal load deliveries to our lay down site at Brown Street.  There will be cable drum deliveries to this site between 29 – 31 March where parking at Brown Street between Douglas Street and Miln Street will be temporarily suspended during short periods of time.  


Traffic will be managed by Contraflow who will remain on the ground during these periods.  I am currently awaiting confirmation of the vehicles’ route from the Dock and also timings, when I am in receipt of this information I will be certain to pass it on to you.”

I will keep residents updated as I hear further from Scottish and Southern Electricity Networks.



Weekly Road Report – West End Ward

DUNDEE CITY COUNCIL – ROAD REPORT FOR THE WEST END 

SUNDAY 12 MARCH 2017

Perth Road (at Roseangle) – temporary traffic lights on Sunday 12 March for Scottish Water mains repair.

WEST END REPORT FOR WEEK COMMENCING MONDAY 13 MARCH 2017

Perth Road (at Arnhall Drive) – temporary traffic lights for 2 weeks for gas main renewal.

Blackness Road (at Rosefield Street) – temporary traffic lights for until midweek  for Scottish Water mains renewal.

Nethergate (West Marketgait to South Tay Street) – closed for 2 weeks for carriageway resurfacing works.

SSE Glenagnes Cable Renewal – Lochee Road lane restrictions and closures on Blinshall Street, Fleuchar Street and Scott Street from Monday 6 March for 5 months.

Perth Road (at Springfield) – temporary traffic lights for one week for footway works.

Patons Lane (Magdalen Yard Road for 40m North) – closed from Monday 13 March for 5 working days for gas service connection works.



Weekly Road Report – West End Ward

DUNDEE CITY COUNCIL – WEEKLY ROAD REPORT

REPORT FOR WEST END WARD WEEK COMMENCING MONDAY 6 MARCH 2017

Perth Road (at Arnhall Drive) – temporary traffic lights for 3 weeks for gas main renewal.

Blackness Road (at Rosefield Street) – temporary traffic lights for one week for Scottish Water mains renewal.

Nethergate (West Marketgait to South Tay Street) – closed for 2 weeks for carriageway resurfacing works.

SSE Glenagnes Cable Renewal – Lochee Road lane restrictions and closures on Blinshall Street, Fleuchar Street and Scott Street from Monday 6 March for 5 months.

Nethergate (at West Marketgait) – closed off-peak (9.30 – 3.30pm) on Thursday 9 and Friday 10 March for cycling works.

Perth Road (at Springfield) – temporary traffic lights for 2 weeks for footway works.



Weekly Road Report – West End Ward

DUNDEE CITY COUNCIL – WEEKLY ROAD REPORT

REPORT FOR WEST END WARD WEEK COMMENCING MONDAY 27 FEBRUARY 2017

Perth Road (at Arnhall Drive) – temporary traffic lights for 2 weeks for gas main renewal.

Blackness Road (at Glenagnes Road) – temporary traffic lights for one week for Scottish Water mains renewal.

Nethergate (West Marketgait to South Tay Street) – closed for 3 weeks from Monday 27 February for carriageway resurfacing works.

Riverside Drive at airport – off-peak temporary traffic lights on Tuesday 28 February for maintenance to Department of Transport monitoring site.

Forthcoming Roadworks

SSE Glenagnes Cable Renewal – Lochee Road lane restrictions and closures on Blinshall Street, Fleuchar Street and Scott Street from Monday 6 March for 5 months.