The Chief Executive in Council has approved a scheme for the sewerage works for Hung Shui Kiu/Ha Tsuen New Development Area Stage 1 Works – Site Formation and Engineering Infrastructure (formerly known as Hung Shui Kiu New Development Area Stage 1 Works – Site Formation and Engineering Infrastructure). Approval of the sewerage scheme was gazetted today (January 24).
The sewerage scheme comprises construction of about 360 metres of sewage rising mains, a sewage pumping station, about 1 700m of gravity sewers, associated manholes and other ancillary works. Construction works for the scheme by the Civil Engineering and Development Department are to be carried out in conjunction with the proposed road works of Hung Shui Kiu/Ha Tsuen New Development Area Stage 1 Works – Site Formation and Engineering Infrastructure.
Details of the sewerage scheme were published in the Government Gazette on December 28, 2018, and January 4, 2019.