Earlier this year, I advised that a positive by-product of the flooding defence works now nearing completion along Riverside Drive was that my request to have the long unmade parking area to the west of the above area would be properly surfaced for the first time, greatly increasing the amount of parking with a quality surface.
The council’s Head of Design & Property and City Engineer has now updated me :
“Half of the area has been surfaced with bituminous material and formally marked out as a car park providing 65 spaces within that area. This is in addition to the 26 spaces at the Bridgeview Café area.
In the other half to the west, which is yet to be opened as a further overflow car park of a similar capacity, the surface is to be sub-base material as per the Yeaman Shore car park. If required in the future, the area to the west can be formally surfaced and marked out.
The contractor is currently using the sub-base area to the west for storage and still has some finishing work to the sub-base to complete.”
Follow this news feed: Fraser Macpherson