Nethergate roadworks today – temporary traffic order

From the City Council :

THE ROAD TRAFFIC REGULATION ACT 1984 : SECTION 14(1)

THE DUNDEE CITY COUNCIL AS TRAFFIC AUTHORITY being satisfied that traffic on the road should be prohibited by reason of water service works being carried out HEREBY PROHIBIT the driving of any vehicle in Nethergate (from its junction with West Marketgait to its junction with South Tay Street), Dundee.

This notice comes into effect on Sunday 19 February 2017 for one day.

Pedestrian thoroughfare will be maintained.

Access to premises will be maintained where possible.

Alternative routes for vehicles are available via West Marketgait/ Hawkhill/Hunter Street/Old Hawkhill/South Tay Street and reverse.

For further information contact 433168.

Executive Director of City Development
Dundee City Council



Weekly Road Report – West End Ward

DUNDEE CITY COUNCIL – WEEKLY ROAD REPORT

REPORT FOR WEST END WARD FOR SATURDAY 18 AND SUNDAY 19 FEBRUARY 2017

Blackness Road (at Wilkie’s Lane) – temporary traffic lights on Sunday 19 February for mobile platform operations.

Nethergate (West Marketgait to South Tay Street) – closed on Sunday 19 February for water supply connection works.

REPORT FOR WEEK COMMENCING MONDAY 20 FEBRUARY 2017

Perth Road (at Arnhall Drive) – temporary traffic lights for 3 weeks for gas main renewal.

Blackness Road (at Glenagnes Road) – temporary traffic lights for 2 weeks for Scottish Water mains renewal.

Shaftesbury Road (at Seymour Street) – closed on Tuesday 21 February for 3 days for Scottish Water repair work.

Hunter Street – temporary traffic lights from Tuesday 21 February for one week for Scottish Water repair.

Forthcoming Roadworks

Nethergate (West Marketgait to South Tay Street) – closed for 3 weeks from Monday 27 February for carriageway resurfacing works.



Temporary Traffic Order – Shaftesbury Road

From the City Council :

THE ROAD TRAFFIC REGULATION ACT 1984 : SECTION 14(1)

THE DUNDEE CITY COUNCIL AS TRAFFIC AUTHORITY being satisfied that traffic on the road should be prohibited by reason of Scottish Water repair works being carried out HEREBY PROHIBIT the driving of any vehicle in Shaftesbury Road (from Seymour Street to approx. 35 metres in a westerly direction), Dundee.

This notice comes into effect on Tuesday 21 February 2017 for three working days.

No pedestrian thoroughfare will be maintained.

Diversion routes for vehicles and pedestrians are available via Seymour Street / Speed Street / Hyndford Street.

For further information contact 433082.

Executive Director of City Development
Dundee City Council



Balgay Road/Scott Street pavement improvements

Having, on behalf of residents, raised the poor condition of pavements along Balgay Road and in the short west part of Scott Street west of Balgay Road (towards the Balgay Park entrance) in the past, I am pleased to see the long-awaited resurfacing now being completed.

Here’s a plan of the works kindly supplied to me by Tayside Contracts and a couple of photos of the works :





Blackness Road area – roadworks clarification

Residents will have noted that the temporary traffic lights on Blackness Road at the Glamis Road/Glamis Drive roundabout (see right) have disappeared.     However, this is unfortunately not because the works by Scotland Gas Networks (SGN) are completed.

I have been updated by Scotland Gas Networks’ Team Manager as follows :

“Unfortunately our work at the Glamis Road roundabout is well behind schedule due to the ground conditions we are encountering.   However, as Scottish Water (SW) is programmed to start in Blackness Road shortly which would conflict with our work, we are lifting the traffic management at the roundabout before they start and will return to complete our work here after SW have finished.  

In the meantime we will be continuing on Glamis Road itself as this won’t disrupt traffic, and will also be returning to Perth Road to complete the service works and mains abandonment which we had to abort previously.

Scottish Water is starting Blackness Road 20th February for approximately 2 weeks so we’ll be back at the roundabout probably mid March for about 2 weeks.”

The Scottish Water work is further east on Blackness Road.   The City Council has further updated me as follows : 

“The SW work will start 20 February at Glenagnes Road junction.    The second week they will move south to Rosefield Street for the second week.
Once SW is complete on their section of Blackness Road, SGN will return to Blackness Road Glamis with their original set up to complete works there. 
As SGN intimated, it will utilise the two weeks of 20/27 February, when SW are in Blackness Road, to complete the remaining services connections left behind in Perth Road at Arnhall Drive area.”