Weekly Road Report – West End Ward #dundeewestend

DUNDEE CITY COUNCIL – WEEKLY ROAD REPORT


REPORT FOR THE WEST END WARD – WEEK COMMENCING MONDAY 12 SEPTEMBER 2022

Miller’s Wynd – closed at its junction with Hawkhill for major construction works. Start date Monday 27 June for 6 months.

Hillcrest Road – closed at No 23 until 20 September for redevelopment works on existing house. Closures will be intermittent and each should last no more than several days.

City Road (Tullideph Place to Logie Street) – closed for up to one week for Scottish Water emergency works.

Cleghorn Street at junction of Rosebery Street – 4 way temporary traffic lights from Monday 5 September for 4 days for CityFibre work.

Milnbank Road at Forest Park Place – 3 way temporary traffic lights from Tuesday 6 September for 2 days for CityFibre work.

Milnbank Road between Bankmill Road and Rosefield Street – road closed from Thursday 8 September for 2 days for CityFibre work.

Easson’s Angle – road closed from Monday 12 September for 6 days for CityFibre work.

Lochee Road – pedestrian lights and road narrowing from Monday 12 September for 4 days for CityFibre work.

Hawkhill (at Peddie Street) – temporary traffic lights Monday 12 (9am) to Tuesday 13 September (6am) for Scottish Water work.

Polepark Road – closed from its junction with Lochee Road to its junction with Milnbank Road (in a southerly direction only) for footway resurfacing works commencing Friday 16th September for 2 weeks.

Forthcoming Roadworks

Fyffe Street – temporary traffic lights from Monday 19 September for 3 days for CityFibre work.

Hillside Road (junction with Hillside place) – closed from Monday 26 September for 3 days for carriageway resurfacing works.

Lower Pleasance – road closure from Monday 3 October for 5 days for CityFibre work.

Nethergate (West Marketgait to Union Street) – closed from Monday 10 October for 9 days for carriageway resurfacing works.

Blackness Road (at junction with Balgay Road) – closed from Wednesday 19 October for 3 days to facilitate carriageway resurfacing works.



Temporary Traffic Order – Polepark Road


From the City Council :

Dundee City Council proposes to make an Order under Section 14(1) of the Road Traffic Regulation Act 1984 for the purpose of facilitating footway resurfacing works. The Order is expected to be in force for two weeks from 16 September 2022. Its maximum duration in terms of the Act is eighteen months.

The effect of the Order is to prohibit temporarily all southbound vehicular traffic in Polepark Road from its junction with Lochee Road to its junction with Milnbank Road.

An alternative route will be available via Lochee Road, East Marketgait, Hawkhill, Horsewater Wynd, Guthrie Street and Brook Street.

If you have any queries, please contact the Network Management Team, City Development Department, Dundee House, 50 North Lindsay Street, Dundee, DD1 1LS – phone 433168.




Temporary Traffic Order – Easson’s Angle and Fleuchar Street

From the City Council :

Dundee City Council proposes to make an Order under Section 14(1) of the Road Traffic Regulation Act 1984 for the purpose of facilitating City Fibre duct installation works. The Order is expected to be in force for eight days from 12 September 2022. Its maximum duration in terms of the Act is eighteen months.
The effect of the Order is to prohibit temporarily all vehicular traffic in (1) Eassons Angle from Fleuchar Street to Milnbank Road and (2) Fleuchar Street at its junction with Eassons Angle.
An alternative route will be available via Milnbank Road, City Road, Cleghorn Street and Benvie Road.
If you have any queries, please contact the Network Management Team, City Development Department, Dundee House, 50 North Lindsay Street, Dundee, DD1 1LS – phone 433082.




Getting things done – Invergowrie Drive #dundeewestend

Fraser is pictured in Invergowrie Drive where a parts of the waiting restrictions have become faded – particularly in the cul-de-sacs.


We contacted the Roads Maintenance Partnership about this and were given the following positive response :

“I have been in touch with Tayside Contracts to have the double yellow lines on Invergowrie Drive – including the cul de sacs – refreshed.”

We are pleased to say this work was undertaken last week.



Temporary Traffic Order – Milnbank Road

From the City Council :


THE ROAD TRAFFIC REGULATION ACT 1984 – SECTION 14(1)

THE DUNDEE CITY COUNCIL AS TRAFFIC AUTHORITY being satisfied that traffic on the road should be prohibited by reason of City Fibre duct installation works being carried out HEREBY PROHIBIT the driving of any vehicle in Milnbank Road (from Rosefield Street to Forest Park Road), Dundee.

This notice comes into effect on Thursday 8 September 2022 for 3 working days.

Pedestrian thoroughfare will be maintained.

Alternative routes for vehicles are available via Rosefield Street / Blackness Road / Forest Park Road.

For further information contact 433082.

Executive Director of City Development
Dundee City Council