DUNDEE CITY COUNCIL – WEEKLY ROAD REPORT
REPORT FOR THE WEST END WARD – WEEK COMMENCING MONDAY 12 SEPTEMBER 2022
Miller’s Wynd – closed at its junction with Hawkhill for major construction works. Start date Monday 27 June for 6 months.
Hillcrest Road – closed at No 23 until 20 September for redevelopment works on existing house. Closures will be intermittent and each should last no more than several days.
City Road (Tullideph Place to Logie Street) – closed for up to one week for Scottish Water emergency works.
Cleghorn Street at junction of Rosebery Street – 4 way temporary traffic lights from Monday 5 September for 4 days for CityFibre work.
Milnbank Road at Forest Park Place – 3 way temporary traffic lights from Tuesday 6 September for 2 days for CityFibre work.
Milnbank Road between Bankmill Road and Rosefield Street – road closed from Thursday 8 September for 2 days for CityFibre work.
Easson’s Angle – road closed from Monday 12 September for 6 days for CityFibre work.
Lochee Road – pedestrian lights and road narrowing from Monday 12 September for 4 days for CityFibre work.
Hawkhill (at Peddie Street) – temporary traffic lights Monday 12 (9am) to Tuesday 13 September (6am) for Scottish Water work.
Polepark Road – closed from its junction with Lochee Road to its junction with Milnbank Road (in a southerly direction only) for footway resurfacing works commencing Friday 16th September for 2 weeks.
Forthcoming Roadworks
Fyffe Street – temporary traffic lights from Monday 19 September for 3 days for CityFibre work.
Hillside Road (junction with Hillside place) – closed from Monday 26 September for 3 days for carriageway resurfacing works.
Lower Pleasance – road closure from Monday 3 October for 5 days for CityFibre work.
Nethergate (West Marketgait to Union Street) – closed from Monday 10 October for 9 days for carriageway resurfacing works.
Blackness Road (at junction with Balgay Road) – closed from Wednesday 19 October for 3 days to facilitate carriageway resurfacing works.